Construction Discussion Forum

Image

The Construction Discussion Forum provides an opportunity for everyone involved with the construction industry to say what they're doing to improve health and safety in the industry, share best practice and enlist the help of other forum members in finding solutions for their problems.

The forum is open to everyone involved with the industry, including designers, contractors, clients, suppliers and site workers. It has been designed to be a useful self-help forum where everybody can contribute from their own practical experience to help and advise others. It provides access to a wide range of expertise to help you tackle health and safety issues.

Join this community

If you would like to take part in discussions, either by starting a new message yourself, or replying to a previous message, you need to be a member of the Construction Discussion Forum. If you would like to become a member, please follow our simple registration process".

Community Information

NameConstruction Discussion Forum
The Construction Discussion Forum provides an opportunity for everyone involved with the construction industry to say what they're doing to improve health and safety in the industry, share best practice and enlist the help of other forum members in finding solutions for their problems.
PrivacyThe community is visible to anyone. Anyone may join this community
Managersconstruction-manager@webcommunities.hse.gov.uk

What's New

  • RE: CDM liablity
    I think you may be over egging it as a generality Frank? These days where a CPP is required for any work by the sole contractor or managing contractor
    Created by Bill Sowerbutts (yesterday at 18:06)
  • CDM liablity
    Yes Clare you are correct. A CPP cannot reasonably be produced without the client pre-construction information included. that is where the client dut
    Created by Frank (yesterday at 15:54)
  • CDM liablity
    Hi I have to agree with the comments already posted on here but ....wouldn't the CPP have included details of how you proposed to mitigate existing r
    Created by Clare (yesterday at 14:58)
  • CDM Regulatory Distortion?
    We politely refuse these terms of engagement or qualify/amend them to align with the CDM regulations. Most Clients are happy with that as their intent
    Created by Safety Provisions (yesterday at 10:50)
  • CDM liablity
    HS(G)47 - download free and follow it.
    Created by gerard (yesterday at 09:17)